To finish a certain job in 8 days, 6 workers are needed. If it is required to finish the same job in 2 days advance, how many workers have to work? *
8 points

Respuesta :

Answer:  96 workers

Step-by-step explanation:

First you multiply 8 and 6 then by 2.

8 x 6= 48

48 x 2= 96

96 workers to help the business