What cycle time would match capacity and demand if demand is 167 units a day, there are 1 shift(s) of 452 minutes each, and workers are given three 45 minute breaks during each shift, one of which is for lunch or dinner

Respuesta :

Answer:

1.90

Explanation:

Calculation for What cycle time would match capacity and demand

First step is to calculate Total break time per shift

Total break time per shift=3*45minute

Total break time per shift= 135 minutes

Now let the cycle time using this formula

Cycle time=Shift Time-Total break time per shift/Demand

Let plug in the formula

Cycle time=452 minutes-135 minutes/167 units

Cycle time=317/167 units

Cycle time=1.898

Cycle time=1.90 (Approximately)

Therefore the cycle time would match capacity and demand is 1.90